Sunderland arena project enters final stages ahead of December reopening

DARRYL KNIGHT Local Journalism Initiative Reporter for The Standard
BROCK: A grand opening, for the expanded Sunderland Memorial Arena, is now planned for Saturday, December 19th. The first tournament is scheduled for the following day, as the long-awaited renovation project moves toward completion.
The revised timeline pushes the reopening back, approximately two weeks, from the original target of the week of December 7th. The Township of Brock confirms several outstanding building and life safety requirements must still be met before the facility can welcome users.
In a project update, issued on Friday, November 13th, the Township said, testing, reporting, and construction-stage documentation required under the Ontario Building Code are being finalized, before the Chief Building Official can issue an occupancy permit.
Once approval is obtained, staff can begin: training on the new ice plant equipment, installing ice, and completing the remaining finishing work.
Mayor Mike Jubb said, the revised timeline should be viewed in the context of the scale of the project, which was initially projected to take between 12 and 18 months. At approximately 13 months, the project remains within the original timeframe.
"The two-week delay will be well worth it," Mayor Jubb said, noting the Township has also invested an additional $1 million in a lengthy list of improvements which will further enhance the facility.
"When you're dealing with a project of this magnitude, and an older building, you're always going to run into unexpected issues," He explained.
Following an on-site meeting, involving: the Sunderland Lions Club, the Brock Minor Hockey Association, the Sunderland Ringette Association, Township staff, engineers, contractors, and other project partners, it was agreed to maintain the existing two-arena ice schedule, until January 2nd, 2027. A full three-arena schedule will take effect after that date.
Mayor Jubb said, he was pleased to confirm the December 19th grand opening and the first tournament, to take place on Sunday, December 20th, while thanking residents and project partners for their patience and understanding.
Local sports organizations are also looking forward to returning to the expanded facility.
Brock Minor Hockey Association president, Matt Gross said, the organization is excited to welcome players and families back to the arena.
"We appreciate the continued collaboration, with Township staff, the Sunderland Lions Club, and fellow user groups, as we work toward a safe reopening and a return to a full three-arena schedule in January," Mr. Gross said.
Sunderland Ringette Association president, Amanda Keeler echoed that enthusiasm, saying, “the organization is looking forward to welcoming the ringette community back to the facility.”
The Sunderland Lions Club, which has played a central role in bringing the project to fruition, also welcomed the approaching completion.
Ralph Maleus, chair of the Sunderland Lions Charitable Foundation, said, “the Lions Club and its companion foundation have worked with the Township for approximately 15 years to advance the project.”
That work initially involved securing federal and provincial government funding, followed by confirming the municipality's contribution. The organizations then turned to Sunderland-area residents, businesses, and community groups to raise the final $1 million needed to move the project forward.
"The response was truly amazing, and we are overjoyed the doors, to our newly expanded and renovated Sunderland Memorial Arena, will soon be open to the Community," Mr. Maleus added.
The renovation and expansion represent a significant investment in local recreation, with the upgraded facility expected to provide a more modern, accessible, and sustainable space for residents and arena user groups.
For now, the focus remains on completing the outstanding safety requirements and securing the necessary occupancy approval, ahead of the planned December opening.